Northmont City Schools New H.S. & PK-1

Project Details

Construction Start Date:
July 2012 (PK-1)
July 2013 (H.S.)
Completion Date:
September 2014 (PK-1)
December 2015 (H.S.)
Construction Cost:
$89,761,577 Budget
Construction Type:
Construction Management

Project Contacts

Owner:

Northmont City Schools
4001 Old Salem Avenue, Englewood, Ohio 45322 Tel: 937-832-5000, Contact: Dr. Sarah Zatik, Supt.

Architect:

Ruetschle/App Architects
222 Linwood Street, Dayton, Ohio 45405
Tel: 937-461-5390, Contact: Mike Huff (Reutschle) or Marianne Webber (App)

Construction Manager:

Shook Touchstone, LLC
Tel: 937-276-6666, PM: Matt Huelsman, Superintendent: Jerry Roark

Project Scope

This project consists of a new 9-12 high school (270,000 SF) and a new PK-1 Kleptz Early Learning Center (100,000 SF). The PK-1 facility is located adjacent to the existing YMCA on a new site with multiple courtyards and an outdoor classroom The high school was constructed on the existing school campus and was completed in four phases.

Project Accomplishments

  • Both projects are targeting LEED Silver certifiation through the United States Green Building Council.