Taylor Univ. Gerig Hall HVAC Replacement

Project Details

Construction Start Date:
March 2013
Completion Date:
August 2013
Construction Cost:
$791,020
Construction Type:
Design-Build w/Fanning Howey Architects

Project Contacts

Owner:

Taylor University
236 W. Reade Ave, Upland, IN 46989
Tel: 765-998-5118, Contact: Ron Sutherland

Architect:

Fanning Howey Associates, 9025 N. River Road, #200, Indianapolis, IN 46240
Tel: 317-848-0966, Contact: Chuck Tyler

Design Builder:

Touchstone Fanning Howey
Tel: 419-228-7272, Project Mgr.: Chris Moore, Superintendent: Dale Niemeyer

Project Scope

This is a design-build project consisting of a 40,000 square foot HVAC replacement project for Taylor University at Gerig Hall. The project added a new VRF system to the existing building for heating and cooling. The system is tied into a new vertical well/lake loop.

Project Accomplishments

This project was challenging in that it needed completed in a short amount of time to meet the owner's tight schedule requirements. Existing construction required extreme flexibility in the design and location of the equipment, making field coordination during construction very important.